Distribution
Incoming Power
We have 4 supplies on 3 different phases coming to us
- 6 Amp Lighting (P2)
- 16 Amp Water Heater (P1)
- 32 Amp Shower (P2)
- 32 Amp Ring (P3)
The cables run to the first floor and should be tapable there to continue to a Consumer unit int the dirty workshop
I have a draft distribution, we will need to prioritize what parts to tackle first. file_electrical-01.pngdraft_electrical_termination_diagram
Circuit Breaker Box
Our breakers are located in a box.
Peter generously donated a consumer unit for us. The best place for it would be in the dirty workshop on the right as you come in the door.
See the drawing above to identify required breakers in the box, there can be expansion
TODO:
- Identify and source breakers.
Ring Main
See drawing above for rings. O think we can get away with three one for each area.
TODO:
- How to run cables between floors.
- Outlets locations
- Conduit size and location
Per Device Breakers
Test Benches
In each area have a test bench which has it's own RCBO
Water Heater
In bathroom and shower, can we get rid of the shower?
Ventilation
A Ventilation Fan and ducting
Heater
Supply for each room.
Future Desires
Is there anything we want in the future that should be considered early on?
- Current consumption monitoring