== Distribution ==
+
{| class="wikitable" style="float:right; margin-left: 10px;"
 +
! Organiser
 +
|-
 +
| [[User:DocOcassi]]
 +
|}
  
 
== Incoming Power ==  
 
== Incoming Power ==  
Line 10: Line 14:
 
* 32 Amp Ring (P3)
 
* 32 Amp Ring (P3)
  
The cables run to the first floor and should be tapable there to continue to a Consumer unit in the dirty workshop, the 16 could be changed for a 32.
+
The cables run to the first floor and should be tapable there to continue to a Consumer unit in the dirty workshop, the 16 could be changed for a 32. though this would require replacement of the cable.
  
Potentially we could change the breaker upstairs to 40 and use a 38, breaker in out box which would remove the risk of tripping the breaker upstairs bu distributed load.
+
Potentially we could change the breaker upstairs to 40A and use a 32A breaker in our box which would remove the risk of tripping the breaker upstairs by distributed load.
  
 +
<!--
 
I have a initial draft distribution setup,  we will need to prioritize what parts to tackle first.
 
I have a initial draft distribution setup,  we will need to prioritize what parts to tackle first.
 
[[:File:Electrical-01.png | Draft Electrical Termination Diagram]]
 
[[:File:Electrical-01.png | Draft Electrical Termination Diagram]]
 +
-->
  
== Circuit Breaker Box ==
+
I have a JB for the wall On the first floor though no terminals as jey I also have one length og 6mm cable for to provide a power for to the consumer unit below, it is run but not connected
Our breakers are located in a box.
 
  
Peter generously donated a consumer unit for us. The best place for it would be in the dirty workshop on the right as you come in the door.
+
== Consumer Unit ==
  
See the drawing above to identify required breakers in the box, there can be expansion
+
We have a schnider Easy9 Distribution box in the hall next to the dirty workshop
 +
<p style="padding:2px;">
 +
<span style="background:#FFF;color:#000;text-decoration:overline">
 +
[[File:M2-3.JPG|400px|middle|Board and beginning of conduit]]
 +
</span></p>
  
TODO:
+
== Distribution ==
 
 
* Identify and source breakers.
 
  
== Ring Main ==
+
This will be done by 50mmx50mm Conduit you can see the plan for distribution below, Iain did some good work mounting the first section of trunking and Consumer unit, you can also see the board for work to be done.
  
See drawing above for rings. O think we can get away with three one for each area.
+
<p style="padding:2px;">
 +
<span style="background:#FFF;color:#000;text-decoration:overline">
 +
[[File:Floorplan-Conduit.png|400px|middle|Conduit]]
 +
</span></p>
  
TODO:
+
=== Lighting ===
  
* How to run cables between floors.
+
see [[EngageSpace/Lighting|Lighting]]
* Outlets locations
 
* Conduit size and location
 
  
== Per Device Breakers ==
+
The main light will be fed from a 6A Breaker, this has not bee done yet, as there is a supply form above which is seperate from out Consumer unit as yet.
  
=== Test Benches ===
+
=== Main Power Distributon ===
  
In each area have a test bench which has it's own RCBO
+
We need to see what we need, I think this should be done in 2.5mm cable with a 20A breaker for each area or by requirement, we will have to consider upstream it we require more load.
  
 
=== Water Heater ===
 
=== Water Heater ===

Latest revision as of 15:32, 11 June 2018

Organiser
User:DocOcassi

Incoming Power

We have 4 supplies on 3 different phases coming to us

  • 6 Amp Lighting (P2)
  • 16 Amp Water Heater (P1)
  • 32 Amp Shower (P2)
  • 32 Amp Ring (P3)

The cables run to the first floor and should be tapable there to continue to a Consumer unit in the dirty workshop, the 16 could be changed for a 32. though this would require replacement of the cable.

Potentially we could change the breaker upstairs to 40A and use a 32A breaker in our box which would remove the risk of tripping the breaker upstairs by distributed load.


I have a JB for the wall On the first floor though no terminals as jey I also have one length og 6mm cable for to provide a power for to the consumer unit below, it is run but not connected

Consumer Unit

We have a schnider Easy9 Distribution box in the hall next to the dirty workshop

Board and beginning of conduit

Distribution

This will be done by 50mmx50mm Conduit you can see the plan for distribution below, Iain did some good work mounting the first section of trunking and Consumer unit, you can also see the board for work to be done.

Conduit

Lighting

see Lighting

The main light will be fed from a 6A Breaker, this has not bee done yet, as there is a supply form above which is seperate from out Consumer unit as yet.

Main Power Distributon

We need to see what we need, I think this should be done in 2.5mm cable with a 20A breaker for each area or by requirement, we will have to consider upstream it we require more load.

Water Heater

In bathroom and shower, can we get rid of the shower?

Ventilation

A Ventilation Fan and ducting

Heater

Supply for each room.

Future Desires

Is there anything we want in the future that should be considered early on?

  • Current consumption monitoring