Difference between revisions of "EngageSpace/Power"

From 57North Hacklab

m (Incoming Power)
Line 10: Line 10:
 
* 32 Amp Ring (P3)
 
* 32 Amp Ring (P3)
  
The cables run to the first floor and should be tapable there to continue to a Consumer unit in the dirty workshop, the 16 could be changed for a 32.
+
The cables run to the first floor and should be tapable there to continue to a Consumer unit in the dirty workshop, the 16 could be changed for a 32. though this would require replacement of the cable.
  
Potentially we could change the breaker upstairs to 40 and use a 38, breaker in out box which would remove the risk of tripping the breaker upstairs bu distributed load.
+
Potentially we could change the breaker upstairs to 40A and use a 32A breaker in our box which would remove the risk of tripping the breaker upstairs by distributed load.
  
 +
<!--
 
I have a initial draft distribution setup,  we will need to prioritize what parts to tackle first.
 
I have a initial draft distribution setup,  we will need to prioritize what parts to tackle first.
 
[[:File:Electrical-01.png | Draft Electrical Termination Diagram]]
 
[[:File:Electrical-01.png | Draft Electrical Termination Diagram]]
 +
-->
  
== Circuit Breaker Box ==
+
== Consumer Unit ==
Our breakers are located in a box.
 
  
Peter generously donated a consumer unit for us. The best place for it would be in the dirty workshop on the right as you come in the door.
+
We have a schnider Easy9 Distribution box in the hall next to the dirty workshop
  
See the drawing above to identify required breakers in the box, there can be expansion
+
== Distribution ==
  
TODO:
+
This will be done by 50mmx50mm Conduit you can see the plan for distribution below.
  
* Identify and source breakers.
+
<p style="padding:2px;">
 
+
<span style="background:#FFF;color:#000;text-decoration:overline">
== Ring Main ==
+
[[File:Floorplan-Conduit.png|400px|middle|Conduit]]
 
+
</span></p>
See drawing above for rings. O think we can get away with three one for each area.
 
 
 
TODO:
 
 
 
* How to run cables between floors.
 
* Outlets locations
 
* Conduit size and location
 
  
 
== Per Device Breakers ==
 
== Per Device Breakers ==

Revision as of 23:31, 24 May 2018

Distribution

Incoming Power

We have 4 supplies on 3 different phases coming to us

  • 6 Amp Lighting (P2)
  • 16 Amp Water Heater (P1)
  • 32 Amp Shower (P2)
  • 32 Amp Ring (P3)

The cables run to the first floor and should be tapable there to continue to a Consumer unit in the dirty workshop, the 16 could be changed for a 32. though this would require replacement of the cable.

Potentially we could change the breaker upstairs to 40A and use a 32A breaker in our box which would remove the risk of tripping the breaker upstairs by distributed load.


Consumer Unit

We have a schnider Easy9 Distribution box in the hall next to the dirty workshop

Distribution

This will be done by 50mmx50mm Conduit you can see the plan for distribution below.

Conduit

Per Device Breakers

Test Benches

In each area have a test bench which has it's own RCBO

Water Heater

In bathroom and shower, can we get rid of the shower?

Ventilation

A Ventilation Fan and ducting

Heater

Supply for each room.

Future Desires

Is there anything we want in the future that should be considered early on?

  • Current consumption monitoring